Project Details

McMicken Dam Outlet Channel Improvement

Public Meetings

Currently there are no public meetings scheduled for this project.

Past Public Meetings

There are no previous public meetings for this project.
Project Contact: Bobbie Ohler
Region: NW
District:
Phase: Design & Engineering
Description:

The McMicken Dam Project includes McMicken Dam itself (approximately 9.5 miles in length), the McMicken Dam Outlet Channel (approximately 6 miles in length) and the McMicken Dam Outlet Wash (approximately 4 miles in length) which discharges to the Agua Fria River.

The Wittmann Area Drainage Master Plan recommended that the McMicken Outlet Channel be rehabilitated, and the District has authorization to design and construct the improvements. The primary project goals are to design and reconstruct the Outlet Channel so as to mitigate current deficiencies, lower risk, and meet District requirements for flood protection, for the 100-year flood. The project will identify landscaping, aesthetics, and multi-use opportunities within the project area that are compatible with the safe and proper function, operation, and maintenance of the McMicken Dam Outlet Channel. In addition, future efforts may improve some locations of the McMicken Wash.

Status:

The 30% design was completed by AECOM and their subconsultant, Gannett Fleming. Completion of design is being accomplished in-house, and the construction start date will be determined based on funding availability.