Project Details

27th Avenue and Olney Avenue

Public Meetings

Currently there are no public meetings scheduled for this project.

Past Public Meetings

• 3/28/2019
Project Contact: Nazar Nabaty
Region: SW
District: 5 - Steve Gallardo
Phase: Design & Engineering
Description:

The District conducted the Laveen Area Drainage Master/Plan Update (ADMP/U) to develop and evaluate solutions to mitigate flooding hazards in the Laveen Area. This project is one of the recommend solutions from the ADMP/U to reduce the impacts from flooding.
This project consists of the design and construction of a storm drain along Olney Avenue from west of 23rd Avenue to 27th Avenue, extending north along 27th Avenue to South Mountain Avenue. The storm drain will outfall into the existing City of Phoenix basin located at the northeast corner of 27th and South Mountain Avenues. The project also includes the design and construction of three retention basins along 23rd Avenue, south of Olney.
The District will be the lead agency for project design and the City of Phoenix is lead on project construction. The City will contribute 50% of the project’s costs. Portions of the project are located within the City of Phoenix and in unincorporated Maricopa County.

Status:

23rd Ave Basins
Design for the Basins has begun and is expected to be completed in September 2019.
Construction of all three Basins has begun and is expect to be completed in October 2019.
City of Phoenix is the lead agency for the construction.

27th Ave Storm Drain
Design for the Storm Drain is expected to start in June 2019.
The District is the lead agency for the design and construction.

Available Documents

Document Name Type Size
Project Overview Map PDF 2.6MB
Public Meetings Notice PDF 8755 KB


Send us your questions or comments about this project.