Project Details

19th Avenue and Dobbins Road Storm Drain Project

Public Meetings

Currently there are no public meetings scheduled for this project.

Past Public Meetings

There are no previous public meetings for this project.
Project Contact: Nazar Nabaty
Region: SW
District: 5 - Steve Gallardo
Phase: Design & Engineering
Description:

The District conducted the Laveen Area Drainage Master Plan/Update (ADMP/U) to develop and evaluate alternative solutions to mitigate flooding hazards in the Laveen Area. This project is one of the recommend solutions from the ADMP/U to reduce the impacts from flooding.


This project consists of the design and construction of a storm drain system along Dobbins Road from west of 15th Avenue to 19th Avenue, extending north along 19th Avenue to South Mountain Avenue, then heading west along South Mountain Avenue to outfall into the existing City of Phoenix regional basin located at the northeast corner of 27th and South Mountain Avenues. The project also includes the design and construction of a new detention basins (Dobbins Basins) along 15th Avenue, south of Dobbins Road.


The District will be the lead agency for design and construction of the project, with the City of Phoenix contributing 50% of the project costs.

Status:

The District is starting the process of IGA with City of Phoenix.



Send us your questions or comments about this project.