Project Description:
This project will construct a concrete low flow channel within the existing, grass-lined East Maricopa Floodway, extending from Guadalupe Road at the upstream end to just south of Ray Road at the downstream end.
The slope of the channel is very flat, resulting in ponding of water and muddy conditions. Concerns about mosquitos been received from adjacent neighborhoods.
The concrete low flow channel will eliminate most of the ponding and muddy conditions, facilitate sediment and debris removal as well as other maintenance activities.
Last Updated: 7/17/2024 9:10:02 AM
Project Updates
Construction is ahead of schedule
Posted On: 9/27/2022 10:10:45 AM
Despite a brief shutdown due to monsoon activity, construction is proceeding well and is currently ahead of schedule with crews now working north of Elliot Rd.
Construction Start
Posted On: 3/14/2022 11:41:03 AM
Public Meetings
There are no public meetings scheduled.
Project Documents
Document Name | Description | Document Type | Filesize | Posted On | |
---|---|---|---|---|---|
Project Location | Map showing the limits of the Project | JPG | 3/14/2022 12:22:12 PM | View |