Projects
Project Name: 51st Ave & Dobbins Road Drainage Improvement Project
112
Project Manager: Tim Murphy
Contact by phone at (602) 506-4605 or by email
Project is in Supervisor District:
- District 1: False
- District 2: False
- District 3: False
- District 4: False
- District 5: True
You can find your Supervisor District by clicking here.
Project Type: Engineering/Design
Project Description:
This project consists of the design and construction of new storm drain pipe with inlets and the construction of Sunrise Basin. The outlet for this system will be the existing Loop 202 freeway drainage basin. The project will provide 100-year flood protection to properties bounded on the west by 59th Avenue, on the south by Sunrise Drive, on the east by 47th Avenue and on the north by Dobbins Road.
The District conducted the Laveen Area Drainage Master Plan/Update (ADMP/U) to develop and evaluate alternative solutions to mitigate flooding hazards in the Laveen Area. This project is one of the recommended solutions from the study to reduce the impacts of flooding.
The District will be the lead agency for design and construction of the project, with the City of Phoenix contributing 50% of the project costs.
Last Updated: 3/28/2022 5:06:25 PM
Project Updates
Right of Way Status
Posted On: 3/28/2022 5:06:25 PM
The Sunrise Basin land acquisition is underway and is anticipated to be complete late Spring 2022.
Design Status:
Posted On: 1/6/2022 3:23:18 PM
The project is anticipated to be advertised for the final design by June 2022.
Intergovernmental Agreement (IGA)
Posted On: 1/6/2022 3:21:46 PM
Project IGA with the City of Phoenix is scheduled for BOD approval on January 12, 2022
Public Meetings
There are no public meetings scheduled.
Project Documents
Document Name | Description | Document Type | Filesize | Posted On | |
---|---|---|---|---|---|
There are no documents attached for this project. |