Project Name: 27th Ave and Olney Ave Storm Drain Project
77
Project Manager: Michael Bouchard
Contact by phone at (602) 506-4592 or by email
Project is in Supervisor District:
- District 1: False
- District 2: False
- District 3: False
- District 4: False
- District 5: True
You can find your Supervisor District by clicking here.
Project Type: Engineering/Design
Project Description:
The project includes designing and constructing a storm drain system along Olney Avenue from west of 23rd Avenue to 27th Avenue and north along 27th Avenue to South Mountain Avenue. The project will outfall to the existing Basin located on the northeast corner of 27th Avenue and South Mountain Avenue. The project also includes designing and constructing three retention basins on 23rd Avenue north of Olney.
The design and construction of retention basins are complete. The design is complete for the storm drain system. The project is currently under construction.
Last Updated: 9/3/2024 1:17:12 PM
Project Updates
Construction Status:
Posted On: 5/23/2023 10:32:43 AM
South Mountain Avenue will be closed between 24th Avenue and 27th Avenue
Monday through Friday, 6AM to 5PM Tuesday, May 30 to Friday, June 16, 2023
TRAFFIC RESTRICTIONS
• South Mountain Avenue will be closed at 27th Avenue. Detour around the closure using 23rd Avenue, Baseline Road, and Dobbins Road.
• Access to residences will be maintained; however, temporary restrictions may occur during regular work hours.
Construction Update: March 2023
Posted On: 3/20/2023 1:24:23 PM
Construction of the storm drain pipe began on Olney Avenue in February and will move north on 27th Avenue to Dobbins Road in March.
TRAFFIC RESTRICTIONS
• The contractor will maintain one lane in each direction on 27th Avenue.
• Access to residences and businesses will be maintained; however, temporary restrictions may occur during regular work hours. Crews will assist vehicles as they enter and exit side streets and driveways.
When passing by the crews operating heavy equipment; whether you are on foot, riding horseback, or in a vehicle, please slow down and watch for direction from the crew.
Construction Status:
Posted On: 10/11/2022 8:55:51 AM
Notice to Proceed is anticipated on the 3rd week of October 2022 to start the construcation.
Construction Status:
Posted On: 8/1/2022 8:17:50 AM
The project advertised for the construction on July 21, 2022 and the bid opening date is scheduled on August 18, 2022.
Construction Status:
Posted On: 3/14/2022 3:07:01 PM
The project is anticipated to be advertised for construction by May 2022.
Design Status:
Posted On: 3/14/2022 3:05:37 PM
The design team is in the process to update the final plans to include new development activities within project area. The plans are expected to be ready for advertisements by April 2022.
Right of Way Status:
Posted On: 7/15/2021 2:13:20 PM
All right of way and temporary construction easements along Olney Ave have been acquired. Acquisition of project right of way along 27th Ave is in process.
23rd Avenue Basins Complete
Posted On: 7/24/2020 12:38:41 PM
Construction of all three Basins was completed in October 2019.
Storm Drain Design Schedule Update
Posted On: 7/24/2020 12:29:03 PM
Design for the storm drain continues and is expected to be completed in August 2020. The District is the lead agency for both design and construction.
Construction will start upon completion of all utility relocation and right-of-way acquisitions.
Public Meetings
Meeting Title: 27th Ave and Olney Public Meeting
Meeting Description:
Meeting Location: Arizona Lutheran Academy
Address:
6036 South 27th Avenue
City:
Phoenix
Zip:
85041
Meeting Date:
2020-03-11
Meeting Time:
05:30 PM
Meeting Title: 27th Ave and Olney Public Meeting
Meeting Description:
Meeting Location: Cesar Chavez High School | Cafeteria
Address:
3921 W Baseline Rd
City:
Laveen
Zip:
85339
Meeting Date:
2019-03-28
Meeting Time:
05:30 PM
Project Documents
Document Name | Description | Document Type | Filesize | Posted On | |
---|---|---|---|---|---|
Project Area Map | Map of 27th and Olney Ave Storm Drain Project Area | 2 | 7/24/2020 10:47:41 AM | View | |
Project Fact Sheet | Fact Sheet for 27th and Olney Storm Drain Project | 3.5 | 7/24/2020 10:52:58 AM | View | |
27th Avenue & Olney Construction Update | 27th Avenue & Olney Construction Update - March 2023 | 3/20/2023 1:14:50 PM | View |