Project Name: Sun City Drains Reconstruction
95
Project Manager: Frank Hakari
Contact by phone at (602) 506-2943 or by email
Project is in Supervisor District:
- District 1: False
- District 2: False
- District 3: False
- District 4: True
- District 5: False
You can find your Supervisor District by clicking here.
Project Type: Construction
Project Description:
The Project will re-construct the 1,500 ft. long channel along the north side of Olive Ave, from 103rd Ave to 99th Ave. The existing lining, built in the 1960s, is in a distressed condition and will be removed and replaced with a rectangular, reinforced concrete lining. The project improvements also include a maintenance access ramp to the channel bottom, safety railing, and perimeter fencing.
Last Updated: 1/24/2023 3:44:06 PM
Project Updates
Project Status
Posted On: 5/24/2022 8:17:44 AM
Construction is complete.
Project Status
Posted On: 2/10/2022 3:51:40 PM
Project Construction is complete as of November 2021.
Public Meetings
There are no public meetings scheduled.
Project Documents
Document Name | Description | Document Type | Filesize | Posted On | |
---|---|---|---|---|---|
Sun City Drains Construction Notice | Flyer sent to area residents. | 3/5/2021 2:53:00 PM | View |