Project Name: 115th Avenue and Union Hills Drive Drainage Improvements Project

33

Project Manager: Unknown
Contact by phone at or by email

Project is in Supervisor District:

  • District 1: False
  • District 2: False
  • District 3: False
  • District 4: True
  • District 5: False

You can find your Supervisor District by clicking here.

Project Type: Construction

Project Description:

The 115th Avenue and Union Hills Drive Drainage Improvement Project is a partnership between the Flood Control District of Maricopa County (District), the City of Peoria (Peoria), the City of Surprise (Surprise) and the Maricopa County Department of Transportation (MCDOT). The project includes approximately two miles of storm drains, basin improvements, channel improvements, maintenance roads adjacent to the project, and associated structures and features.

The main goal of the project is to intercept flood water that enters the project area from the northeast and convey the water to the Agua Fria River via existing and improved channels and/or storm drains. The project is designed for the 100-year storm event.

The project is located within the City of Peoria, City of Surprise and unincorporated Maricopa County. The project begins at Beardsley Road and 107th Avenue and ends south of Bell Road at the Agua Fria River.

The project is divided into three phases:

Phase 1

Improve the existing Sun City Drain along 115th Avenue from Agua Fria River to Bell Road as needed; widen the channel at the northeast corner of 115th Avenue and Bell Road to ensure the 100-year flood flows travel under the road; improve the channel drainage along 115th Avenue from Bell Road to Union Hills Drive; and add storm drains and catch basins at the intersection of 115th Avenue and Union Hills Drive and north along 115th Ave. to Doodah Lane.

Phase 2

Add a storm drain system along Union Hills Drive from 111th Avenue to 107th Avenue and along 107th Avenue (outletting to the Canyon Ridge Channel); add a storm drain system along 107th Avenue from Union Hills Drive to Palm Tree Drive; and improve the existing basins at the northwest and northeast corners of Union Hills Drive and 111th Avenue.

Phase 3

Improve the existing earthen channel along Beardsley Road from 115th Avenue to 111th Avenue; add a storm drain system along 115th Avenue from Union Hills Drive to Beardsley Road; and add a split flow junction structure at the northeast corner of Beardsley Road and 115th Avenue.

Last Updated: 5/21/2020 3:49:51 PM


Project Updates

Project Status Update
Posted On: 5/21/2020 1:20:51 PM

Construction of Phase 1 and Phase 2 is now complete. Phase 3 is at 30% design and on hold, pending funding availability.


Public Meetings

There are no public meetings scheduled.


Project Documents

Document Name Description Document Type Filesize Posted On  
Project Map Aerial overview of project area PDF 3.2 5/21/2020 1:53:15 PM View
Road Closure Advisory (Jan. 3-29, 2018) Road closure advisory for Jan 2018 for 11th Avenue, between Union Hills Drive and Cimarron Drive. PDF .275 5/21/2020 2:36:27 PM View
Construction Update Project update for May 2017. PDF .23 5/21/2020 2:40:44 PM View
Constuction Update Project update for March 2017. PDF .29 5/21/2020 2:42:55 PM View
Project Mailer Announcement of project and notice of public open house on 11/5/2014 PDF 3.5 5/21/2020 2:46:43 PM View
Project Mailer Announcement of project and notice of public open house on 3/7/2014 PDF 3.7 5/21/2020 2:50:10 PM View
Exhibit Boards Exhibits shown at the March 2014 public meeting PDF 11 5/21/2020 3:37:02 PM View